Plan of Day

Daily Reporting Intelligence

POD-2026-0268

Feb 23, 2026

Daily Project Report

Highway 101 Expansion — Phase 2

At Risk
62°FPartly Cloudy
8 mph
45%

S-Curve Progress

Progress S-Curve

Planned
Actual
Variance
Planned0%
Actual0%
Variance0%
0%25%50%75%100%95%M1M2M3M4M5M6M7M8M9M10M11M12

Activity Status

Activity Status

47 total
0%Complete
Completed
0
In Progress
0
Not Started
0
On Hold
0
Delayed
0

Progress Comparison

Progress Overview

0%
PhysicalWork Complete
0%
EarnedValue Complete
0%
ScheduleTime Elapsed
On track

Project Timeline

0% remaining
0days left
Elapsed0 days
Total Duration400 days
Progress0%
TargetJul 5, 2026

Weather Days & RFI Status

Weather Days

Critical
0of 20
Remaining0 days
Usage Rate0%
Critical path impact: 5d
7-Day Forecast Risk
202
202
!
202
~
202
202

RFI Status

On Target
0%Closed
Closed
0
Open
0
Avg Response
0.0/ 7d
Schedule impact: 2d

Delay Analysis

Delay Analysis

0 total days
0Days
Excusable
0d
Non-Excusable
0d
Liability Exposure0%
WeatherE
0d
Material DeliveryE
0d
SubcontractorNE
0d
Design ChangeE
0d
EquipmentNE
0d
Plan of Day
Day 268Feb 23, 2026
1 / 9

70% of Projects Finish Late

POD tracks planned vs actual in real time. See slippage the day it happens.

0:00 / 1:15